The Darien Department of Public Works' paving schedule is as follows:

Mechanic Street from Sedgewick Avenue to Boston Road: Aug. 7 to 9

Chestnut Street from Noroton Avenue to Fairfield Avenue: Aug. 7 to 9

West Elm Street from Noroton Avenue to Edgerton Street: Aug. 7 to 9

Devonshire Drive from Hillside Avenue to Glenwood Drive: Aug. 8 to 12

Glenwood Drive from Devonshire Drive to Victory Drive: Aug. 8 to 12

Victory Drive from Glenwood Drive to Devonshire Drive: Aug. 8 to 12

Holmes Avenue from West Avenue to Private Holmes: Aug. 8 to 12

Leeuwarden Road from Christie Hill Road to the end: Aug. 9 to 14

More Information

Fact box

Leeuwarden Lane from Leeuwarden Road to the end: Aug. 9 to 14

Kerry Lane from Leeuwarden Road to the end: Aug. 13 to 15

Old Oak Road from Leeuwarden Road to the end: Aug. 13 to 15

Leroy West parking lot: Aug. 14 to 16

The work includes milling and paving. Road surfaces will have raised structures during the work. Motorists and others are asked to avoid those roads if possible or use extra caution. The schedule is based on favorable weather conditions, and emergency access will be available at all times.

Darien police officers will be present to direct traffic and assist area residents during construction. Driveway access will be limited during paving operations. However, no single driveway should be closed for more than an hour. On-street parking will be suspended during paving operations.

For information, call 203-656-7346.